CAUSTIC TRANSFER PIPELINE (QAL)

CLIENT:   QUEENSLAND ALUMINA LIMITED

PROJECT:  CAUSTIC TRANSFER PIPELINE

Owner:  Rio Tinto, Rusal

LOCATION:  Parsons Point Gladstone

Duration: 6 weeks

Project Completion: March 2018

Details

Install New 200NB Caustic Transfer Pipeline from South Trees to Mainland Tie-In.

  • Civil, Structural, and Piping works
  • Supply, fabrication, NDT, protective treatment and deliver to site
  • Over 200m of DN200 pipe
  • Complete Tie-ins with outage windows
  • Provide management, supervision, labour, materials and equipment
  • Daily Timesheeting
  • Scheduling and reporting for the duration of work
  • Assist with commissioning

Highlights

  • All adjacent structures, infrastructure and plant remained in place and in service
  • Works were completed within schedule and estimated budget
  • No LTIs

CAUSTIC TRANSFER PIPELINE (QAL)