CLIENT: QUEENSLAND ALUMINA LIMITED
PROJECT: HID5 PLATE HEAT EXCHANGERS
Owner: Rio Tinto, Rusal
LOCATION: Parsons Point Gladstone
Duration: 4 weeks
Project Completion: June 2018
Details
Relocate and Upgrade 3off Heat Exchangers.
- Civil, Structural, Mechanical, Piping, and Electrical works
- Supply, fabrication, NDT, protective treatment and deliver to site
- Works delayed due to operational requirements
- Works accelerated with day and night shifts when the area became available
- Fatigue Management Plan developed and implemented
- Assist the client and provide flexibility when the work area was not available
- Provide management, supervision, labour, materials and equipment
- Management of subcontractors
- Scheduling and reporting of delays and accelerated works
Highlights
- All adjacent structures, infrastructure and plant remained in place and in service
- Works were completed within the revised schedule and budget
- No LTIs