REFURBISHMENT WORKS (Orica Yarwun)
CLIENT: Orica Mining Services
PROJECT: BOILER UPGRADE
LOCATION: Yarwun
Project Completion: Ongoing
Details
Refurbishment of 100T & 300T Storage Bullets and Bulk Store Tower.
- Offsite supply, fabrication, NDT, surface protection and delivery to site
- Provide project management, supervision, labour and equipment
- Scaffolding, encapsulation, blasting and painting of bullets
- Replacement and refurbishment of pipework and inline devices
- Assistance with determining and setting up of temporary supports
- Installation and removal of a temporary support structure
- Structural and access refurbishment of the tower
- Tower works mobilised & demobilised daily to allow for routine operational requirements
Highlights
- All adjacent structures, infrastructure and plant remained in place
- All works completed with minimal offline time and required daily clearance permits
- No LTIs