REFURBISHMENT WORKS (Orica Yarwun)

CLIENT:  Orica Mining Services

PROJECT:  BOILER UPGRADE

LOCATION:  Yarwun

Project Completion: Ongoing

Details

Refurbishment of 100T & 300T Storage Bullets and Bulk Store Tower.

  • Offsite supply, fabrication, NDT, surface protection and delivery to site
  • Provide project management, supervision, labour and equipment
  • Scaffolding, encapsulation, blasting and painting of bullets
  • Replacement and refurbishment of pipework and inline devices
  • Assistance with determining and setting up of temporary supports
  • Installation and removal of a temporary support structure
  • Structural and access refurbishment of the tower
  • Tower works mobilised & demobilised daily to allow for routine operational requirements

Highlights

  • All adjacent structures, infrastructure and plant remained in place
  • All works completed with minimal offline time and required daily clearance permits
  • No LTIs